Midland Highway 10 Year Action Plan

Roadwork list

Roadworks map

Show only: Zoom

* The existing 3-star rating category means that this section of the Midland Highway has already achieved a 3-star rating on the AusRAP Star Rating assessment (a safety rating system out of five stars). The objective of the Midland Highway 10 Year Action Plan is to achieve an overall 3-star rating across the highway.



Need the latest travel times? Plan your trip here.

Completed works

  • South of Tunbridge Stages 1 and 2 This project improved road safety by implementing works across two stages. Stage one eased a curve south of Tunbridge, while stage two provided an additional south-bound overtaking lane and overall curve improvements. more info view on map
    Current status

    Completed works

    Start of works

    Stage 1: December 2014 and Stage 2: November 2015

    Completion of works

    Stage 1: April 2015 and Stage 2: April 2016

  • Kempton to Melton Mowbray Stage 1 This project improved safety measures between Kempton and Melton Mowbray. more info view on map
    Current status

    Completed works

    Start of works

    January 2016

    Completion of works

    March 2017

  • Mangalore to Bagdad Stage 1 (Bagdad) This project improved the safety of the section of road in the vicinity of Bagdad. Works included a central turning lane through Bagdad and removal of roadside hazards. more info view on map
    Current status

    Completed works

    Start of works

    Early 2016

    Completion of works

    April 2017

  • South of Kempton This project improved the safety of the three-lane section of the highway - north of Constitution Hill. more info view on map
    Current status

    Completed works

    Start of works

    December 2014

    Completion of works

    December 2015

  • South of Spring Hill This project improved road safety by way of road widening to install a flexible safety barrier and extend sealed shoulders. more info view on map
    Current status

    Completed works

    Start of works

    January 2015

    Completion of works

    May 2015

  • North of Spring Hill This project improved road safety by way of road widening to install a flexible safety barrier and extend sealed shoulders. more info view on map
    Current status

    Completed works

    Start of works

    December 2014

    Completion of works

    May 2015

  • Mud Walls Road Junction This project improved road safety by upgrading the left-turn facility at the Mud Walls Road junction. more info view on map
    Current status

    Completed works

    Start of works

    February 2015

    Completion of works

    April 2015

  • Kings Meadows roundabout This project installed a roundabout to improve road safety at the Kings Meadows connection and reduce queuing to the Midland Highway. more info view on map
    Current status

    Completed works

    Start of works

    December 2014

    Completion of works

    Mid-2015

  • Conara to Cleveland Stage 1 This project improved road safety with the installation of a northbound acceleration lane for heavy vehicles turning north from Esk Main Road. more info view on map
    Current status

    Completed works

    Start of works

    December 2014

    Completion of works

    Mid-2015

  • Kempton to Melton Mowbray Stage 2 This project improved safety measures between Kempton and Melton Mowbray. more info view on map
    Current status

    Completed works

    Start of works

    June 2016

    Completion of works

    March 2017

Under construction

  • White Lagoon (Tunbridge) to Mona Vale This project will improve safety between Tunbridge and Mona Vale. Works will include road widening and improving the alignment near Mona Vale. more info view on map
    Current status

    Under construction

    Start of works

    March 2016

    Completion of works

    February 2018

  • Symmons Plains to south of Perth This project will improve the safety of the section of road between Symmons Plains and south of Perth by implementing a range of safety measures. more info view on map
    Current status

    Under construction

    Start of works

    Late 2016

    Completion of works

    Mid-2018

  • Perth-Breadalbane Duplication The Perth to Breadalbane Duplication will provide a divided dual lane highway (four lanes) from Perth to the Launceston Southern Outlet. more info view on map
    Current status

    Under construction

    Start of works

    December 2015

    Completion of works

    Mid-2018

In planning

  • Perth Link Roads This project will improve safety and efficiency by removing heavy vehicles from the centre of Perth as they travel to and from the northern and north-western ports. more info view on map
    Current status

    In planning

    Start of works

    2018

    Completion of works

    2020

  • St Peters Pass to South of Tunbridge This project will improve the safety of the section of road between St Peters Pass and south of Tunbridge. more info view on map
    Current status

    In planning

    Start of works

    Late 2017

    Completion of works

    Summer 2018-2019

  • Epping Forest to Powranna This project will improve the safety of the section of road between Epping Forest and Powranna. more info view on map
    Current status

    In planning

    Start of works

    Late 2017

    Completion of works

    Early 2019

  • Mangalore to Bagdad Stage 2 (Mangalore) This project will improve the safety of the highway between the Pontville roundabout and Eddington Road. more info view on map
    Current status

    In planning

    Start of works

    Summer 2017-2018

    Completion of works

    Early 2019

  • York Plains to St Peters Pass This project will improve the 5 km length of highway from 2 km south of York Plains Road, and continuing to the St Peters Pass rest area. more info view on map
    Current status

    In planning

    Start of works

    Late 2017

    Completion of works

    Summer 2018-2019

Future works

More information

If you would like further information, please contact the Department of State Growth at road.projectenquiries@stategrowth.tas.gov.au