Department of State GrowthRoads for our Future

Midland Highway 10 Year Action Plan

South of Tunbridge Stages 1 and 2

South of Tunbridge Stage 1

The works

This project improved road safety by easing a curve south of Tunbridge, providing a wide central median, and lane separation with a flexible safety barrier.

South of Tunbridge Stage 2 

The works

This project included the provision of an additional south-bound overtaking lane, installation of central and roadside flexible safety barriers, two light vehicle turning bays, and curve improvements.

Current status

Completed works

Start of works

Stage 1: December 2014 and Stage 2: November 2015

Completion of works

Stage 1: April 2015 and Stage 2: April 2016

More information

If you would like further information, please contact the Department of State Growth at road.projectenquiries@stategrowth.tas.gov.au